The environmental and the social impact have yet to be determined, but if it turns out that rare earths and uranium can be safely mined from the Kuannersuit, in southern Greenland, then Greenland Minerals and Energy, an Australian firm, is ready to apply to begin operation – eight years after it first began exploring the area.
“We expect that it’s going to happen early next year,” John Mair, the GME managing director, said earlier this month in connection with the release of the firm’s quarterly report.
A feasibility study shows the mine would be profitable, and it would mean jobs and income for the country. Many, though, are concerned about its environmental impact; opponents have repeatedly demonstrated against the mine, particularly out of concern that radioactive dust kicked up by the uranium the firm will extract as a by-product of the rare-earths mining will make the area unliveable.
SEE RELATED: Uranium opponents look to other sectors for job growth
GME estimates that Kuannersuit could be operational for 37 years, though two adjacent areas could hold as much as a billion additional tonnes of rare earths, which would extend the mine’s lifespan considerably.
According to feasibility studies for the mine, most of its income would come from low-cost production of rare earths. The uranium and other mineral by-products that result from rare-earth extraction would add extra production costs, but the income from their sale will help drive down the production price of the rare earths.
After being mined, the ore will be refined on-site. The rare earth concentrate will then be shipped to China, which houses the world’s only facility capable of carrying out the necessary further processing. Other types of ore will be sent to Europe.
When it comes to the uranium, one of the big concerns has been where it will would end up. Mr Mair, however, expects the process of mining, storing, shipping and selling will meet international guidelines set up to prevent its mis-use.
SEE RELATED: Greenland rare-earth dig to seek final approval by 2016
If all goes according to the firm’s timetable, construction of the mine could start as early as 2017, but, Mr Mair points out, the actual date depends on the approval process.
GME expects the environmental-impact assessment and the social-impact assessment, two studies required by law, to be ready to submit to regulators in October. That would mean being able to file an official application in early 2016.
Public hearings would follow as would negotiations over an impact and benefit agreement, which outlines how the operation will affect the area, and what Nuuk can expect to gain from granting a mining licence.
Should the GME get approval, it is expected that construction of the mine will take two years and require 1,100 workers, at least a portion of whom could come from Greenland.
SEE RELATED: Fear and confusion in Narsaq
Once the mine becomes operational, about half of employees are expected to come from Greenland. In total, the mine and its employees are expected to contribute 400 million kroner ($60 million) annually in taxes.
The environmental and social-impact studies are expected in to be completed in the coming months, and Mr Mair understands that the possibility of the mine opening is making people in the area nervous.
“But we’re doing what we can to keep pollution to a minimum,” he says. “We’re convinced that farming, fishing and all other economic activity will be able to continue as normal after production starts.”
In addition to the presence of radioactive dust, critics are also worried about GME’s plans to deposit tailings, the unseable material left over after valuable minerals are extracted, in a lake near the mine. Mr Mair, however, notes that anything deposited into the lake will have come from the area. “We’re not adding outside pollution,” he says.
SEE RELATED: Power to the people
Getting the mine approved requires proving that it does not pose a health or enviromental risk. Once approved, according to Mr Mair, the firm would continue to conduct regular monitoring of the area. He suggests that concerned residents do the same, so they can see for themselves whether pollution measurements increase.
“Maybe the best thing is for people not to trust the company’s monitoring.”